Construction Work Kick Off

Kruger Energy and Kahnawà:ke Sustainable Energies (KSE) today announced the start of the construction of the Des Cultures Wind Farm, a 24-MW project representing investments of approximately $70M, scheduled to be completed in the fall of 2021 in the municipalities of Saint-Rémi and Saint-Michel, in the Montérégie Region…

Open House for the Start of the Des Cultures Wind Farm Project Construction

With the construction of the Des Cultures Wind Farm about to begin, the citizens of Saint-Michel and Saint-Rémi were invited to an open house event held on the evenings of August 18 and 19 at Kruger Energy’s office in Saint-Rémi.  During the two information sessions where social distancing measures were in place, participants learned more details about the project,…

Government Decree Issued

The Des Cultures Wind Energy Project continues to progress following the announcement of a Québec government decree that authorizes the project. The decree can be viewed here (in French only). Construction of the wind farm will begin in just a few months. This August, public…

BAPE Process Completed

The Des Cultures Wind Farm Project has reached a significant milestone as no public hearing was requested following the public information session held in July 2019 by the Bureau d’audiences publiques sur l’environnement (BAPE). This means that the Des Cultures Wind Farm Project appears to…

Answers to questions

On April 3rd, 2019, the Des Cultures Wind Farm Project team filed answers to questions received back in early March from the Ministère de l’Environnement et de la Lutte contre les changements climatiques (MELCC) in the context of the environmental impact assessment. The document has…