Construction work has advanced significantly at the future Des Cultures Wind Farm despite the pandemic.

Our teams began work at the beginning of September with the construction of access roads, excavation, the installation of the piles and reinforcements as well as the pouring of the foundations for each of the six wind turbines. In the past few weeks, the meteorological tower has been erected.

Construction has therefore advanced according to schedule. There will be a pause for the winter until spring, when we will install the collector system and erect the wind turbines. Commissioning is still scheduled for fall 2021.

The team at Des Cultures Renewable Energy would like to wish you Happy Holidays and thank you for your interest in the Des Cultures Wind Farm Project.

 