Progress Report – Des Cultures Wind Farm Project
Construction work has advanced significantly at the future Des Cultures Wind Farm despite the pandemic. Our teams began work at the beginning of September with the construction of access roads, excavation, the installation of the piles and reinforcements as well as the pouring of the…
Construction Work Kick Off
Kruger Energy and Kahnawà:ke Sustainable Energies (KSE) today announced the start of the construction of the Des Cultures Wind Farm, a 24-MW project representing investments of approximately $70M, scheduled to be completed in the fall of 2021 in the municipalities of Saint-Rémi and Saint-Michel, in the Montérégie Region…
Open House for the Start of the Des Cultures Wind Farm Project Construction
With the construction of the Des Cultures Wind Farm about to begin, the citizens of Saint-Michel and Saint-Rémi were invited to an open house event held on the evenings of August 18 and 19 at Kruger Energy’s office in Saint-Rémi. During the two information sessions where social distancing measures were in place, participants learned more details about the project,…
Government Decree Issued
The Des Cultures Wind Energy Project continues to progress following the announcement of a Québec government decree that authorizes the project. The decree can be viewed here (in French only). Construction of the wind farm will begin in just a few months. This August, public…
BAPE Process Completed
The Des Cultures Wind Farm Project has reached a significant milestone as no public hearing was requested following the public information session held in July 2019 by the Bureau d’audiences publiques sur l’environnement (BAPE). This means that the Des Cultures Wind Farm Project appears to…
Report on the BAPE’s Public Information Session Period Sumitted
The report on the public information period held by the Bureau des audiences publiques du Québec (BAPE) has been posted on the BAPE’s website. You can view the report at this address (French only): https://www.bape.gouv.qc.ca/fr/dossiers/parc-eolien-des-cultures-saint-remi-saint-michel/ A public information session was held in Saint-Rémi on Tuesday,…
Public Information Period On the Des Cultures Wind Farm Project in Saint-Rémi and Saint-Michel
ENVIRONMENTAL IMPACT STUDY AND REVIEW PROCEDURE The Des Cultures Wind Farm Project involves the construction of a wind farm comprising six wind turbines for a total installed capacity of 24 MW. The wind farm is located south of the St. Lawrence River and covers a…
Answers to questions
On April 3rd, 2019, the Des Cultures Wind Farm Project team filed answers to questions received back in early March from the Ministère de l’Environnement et de la Lutte contre les changements climatiques (MELCC) in the context of the environmental impact assessment. The document has…
Another Milestone Reached: Experts’ questions and opinions received
Another milestone has just been reached in the development of the Des Cultures Wind Farm Project, as experts in various ministries that are involved in analyzing the admissibility of our environmental impact assessment have submitted their questions and opinions. This is a normal and beneficial…
Filing of the Environmental Impact Study
The documents of the environmental impact study for the Des Cultures Windfarm are now available on the website of the Ministère de l’Environnement et de la Lutte contre les changements climatiques (MELCC) in the Registry of environmental evaluations. These documents can be accessed at the…