Construction Status Update

Des Cultures Wind Farm Construction

As announced at the open house event on August 18 and 19, construction of the Des Cultures Wind Farm will begin the first week of September. The work scheduled for this fall includes the construction of access roads, as well as excavation and pouring of the foundations for the six future turbines. This page will be updated weekly to keep you up to date.

If you have any questions or concerns, please do not hesitate to reach out to our team:
1-844-668-6818  |  info@projeteoliendescultures.com

Week of November 23, 2020

SAINT-MICHEL

  • Installation of piles for the foundation of the met tower, pouring of concrete and installation of formwork.
  • Steel rebar installation at turbine T4.
  • Steel rebar installation and pouring of concrete for piles at turbine T5.
  • Installation of the concrete slab of the foundation of turbines T5 and T6 and installation of the anchor cage.
  • Steel rebar installation at turbine T6.

SAINT-RÉMI

  • Completion of work area of turbine T1.
  • Backfilling and grounding of the foundation of turbine T1.
  • Pouring of concrete for the foundation of turbine T2 and removing of formwork.
  • Steel rebar installation for the foundation of turbine T3 and installation of formwork.

 

Week of November 30, 2020

SAINT-MICHEL

  • Removal of formwork for the piles for the met tower, backfilling, grounding and preassembly of tower.
  • Installation of formwork and pouring of concrete for the foundation of turbine T4.
  • Steel rebar installation for the foundation of turbines T5 and T6.

SAINT-RÉMI

  • Completion of work area of turbine T2.
  • Backfilling and grounding of the foundation of turbine T2.
  • Pouring of concrete for the foundation of turbine T3 and removal of formwork.

The six turbine locations are indicated on the map below.

Energie_PEDC_Carte_FR_3840x2160_v6F