Construction Status Update

Des Cultures Wind Farm Construction

The Des Cultures Wind Energy Project team is pleased to announce that construction of the Des Cultures Wind Farm has resumed on April 12.

If you have any questions or concerns, please do not hesitate to reach out to our team:
1-844-668-6818  |  info@projeteoliendescultures.com

Week of October 11, 2021 

SAINT-MICHEL

  • Turbine completion:
    • T4, T5 and T6: Inspection.
  • Reclaim of the working area:
    • T4, T5 and T6;
    • Intersections on public roads.

SAINT-RÉMI

  • Turbine erection:
    • T1: Erection of the blades.
  • Turbine completion:
    • T2: Cabling and inspection;
    • T3: Cabling.
  • Cranes:
    • 650T at T1;
    • 130T at T1.

Week of October 18, 2021 

SAINT-MICHEL

  • Turbine completion:
    • T5 and T6: Inspection.
  • Reclaim of the working areas:
    • T4, T5 and T6;
    • Intersections on public roads.

SAINT-RÉMI

  • Turbine completion:
    • T1: Cabling;
    • T2 and T3: Inspection.

The MTQ requires night deliveries for the blades and upper sections of the tower.

Please note depending on the weather, work can be pursued during the weekends.

Wind turbine numbers and infrastructure siting are shown on the project map below.

Energie_PEDC_Carte_FR_3840x2160_v6F

Des Cultures Wind Farm Construction Pictures