Construction Status Update

Des Cultures Wind Farm Construction

As announced at the open house event on August 18 and 19, construction of the Des Cultures Wind Farm will begin the first week of September. The work scheduled for this fall includes the construction of access roads, as well as excavation and pouring of the foundations for the six future turbines. This page will be updated weekly to keep you up to date.

If you have any questions or concerns, please do not hesitate to reach out to our team:
1-844-668-6818  |  info@projeteoliendescultures.com

Week of September 21, 2020

SAINT-MICHEL

  • No work scheduled.

SAINT-RÉMI

  • Installation of piles for turbine T1.
  • Steel rebar installation and pouring of concrete for the piles at turbine T1.
  • Construction of access road to turbine T3.
  • Installation of a culvert for stream crossing on the access road to turbine T3.
  • Preparation of the work area for turbine T3.
  • Installation of a platform that will be used to drive in the piles for turbine T3.

Week of September 28, 2020

SAINT-MICHEL

  • Construction of access road to turbine T5.
  • Stripping of the work area for turbines T4, T5 and T6.
  • Construction of access road to turbine T6.

SAINT-RÉMI

  • Steel rebar installation and pouring of concrete for piles at turbine T1.
  • Installation of piles for turbine T2.
  • Complete the installation of the platform that will be used to drive in the piles for turbine T3.

The six turbine locations are indicated on the map below.

Energie_PEDC_Carte_FR_3840x2160_v6F